Board of Adjustment Quasi Judicial Hearing

NOTICE OF BOARD OF ADJUSTMENT QUASI-JUDICIAL HEARING

TOWN OF WEDDINGTON

NOTICE OF BOARD OF ADJUSTMENT QUASI-JUDICIAL HEARING

Monday, June 29th 2015  – 7:00 PM

WEDDINGTON TOWN HALL

1924 WEDDINGTON ROAD

There will a Board of Adjustment Quasi-Judicial Hearing on Monday, June 29th, 2015 at 7:00 PM at the Weddington Town Hall, 1924 Weddington Road.  The Board of Adjustment will hear a zoning variance request for the property located at 5809 Hemby Road.

Please contact the Town Planner at (704) 846-2709 for additional information.  The Town Hall is open Monday, Wednesday, and Friday – 9:00 a.m. to 1:00 p.m.

                                                                                                                                                                                               By Order of the Town  Council                                                                                                                                                                                                   Peggy Piontek, Town Clerk                

SKM1x1

MUNICIPAL FIRE SERVICE – FAQ's

McGRATH FIRE STUDY

WATER TOWER UPDATE

Please see below schedule for the Hemby Road Water Tower.  This information was received by Union County Public Works.  Currently, the Contractor appears to be on schedule with the site work portion of the Contract.  Union County anticipates in the next three (3) to four (4) weeks that the subcontractor that will be installing the auger cast piles to support the tank will be mobilizing on site to commence with their efforts.  Currently, the site work subcontractor has completed initial grading, construction of the access road, and installation of sediment and erosion control measures.  The contractor has sown temporary seeding and placed straw to stabilize the site according to NCDENR requirements.  At the beginning of December 2014 it is anticipated that the contractor will be taking delivery of piping and start installation of the on- and off-site waterlines that will feed the tank and tie-in existing systems on Hemby Road.

     

TASK

START DATE

END DATE

Engineering/Shop Drawings/Approval

October 06, 2014

January 09, 2015

Tank Material Order/Purchase

November 24, 2014

February 27, 2015

Tank Fabrication & Shipment

March 02, 2015

May 22, 2015

Foundation Construction & Site Work

October 20, 2014

February 13, 2015

Concrete Shaft Construction

February 16, 2015

May 15, 2015

Tank Erection (on ground)

May 18, 2015

September 11, 2015

Paint Tank (on ground)

September 14, 2015

November 06, 2015

Raise Tank

November 09, 2015

December 31, 2015

Paint Tank (in air)

February 22, 2016

April 01, 2016

Sterilize & Test

April 25, 2016

April 29, 2016

Electrical

April 04, 2016

April 29, 2016

Final Site Work

May 02, 2016

May 27, 2016